Residential Inspection Process
1. Footing: Before concrete is poured into footing with grade markers in place (no
wood grade markers).
2. Foundation: Foundation with bolts as per code. 12 inches from corners and 4 feet
on center before dirt is around piers and over footing.
A. Piers After piers are capped (before wood)
B. Concrete slab (1) Before plumbing is covered
(2) When ready to pour concrete
3. Floor: Floor framing is in place just before any floor sheathing and after dirt is
Leveled and crawl space is cleaned and clear of all vegetation and debris.
4. Sheathing /nailing inspection (exterior alls/Osb).
5. Rough-in-Framing: When rough-in plumbing, mechanical and electrical are
installed. All holes around plumbing, mechanical and
electrical work shall be caulked with an approve caulking
before insulation is installed in walls.
6. Insulation: When insulation is installed in walls prior to hanging sheetrock and/or
paneling.
7. Final: General contractor and/or a permit holder to call for final inspection.
When all construction work is completed with vapor barrier installed under
home and ready for certificate of occupancy.
$35.00 fee for 1st reinspection and $70.00 fee for each reinspection thereafter.
Two (2) times permit fee if work is started before permit is issued.
Do not call unless work is ready for inspection.
Call before 5pm for the next day inspection. 658-9538 ext. 111 0r ext. 112.